Planned Ind Reqs (PIRs) mismatch when transferred from APO DP to ECC
Hi Gurus, While transferring PIRs from APO DP to ECC, Numbers in planning book are being multiplied by number of time periods available in data view before reaching ECC. Below are example and...
View ArticleRe: Planned Ind Reqs (PIRs) mismatch when transferred from APO DP to ECC
Tejasvi, Cross check:If UoM is same in APO and ECC. There is no conversion etc. happening (though it's difficult as each product can't have same but cross check to rule out).Just cross check the below...
View ArticleRe: Planned Ind Reqs (PIRs) mismatch when transferred from APO DP to ECC
you are looking at which level and realeasing at what level? when you look numbers are SDP94 what is your header? product and location? and are these the same a aggregation while in the release job...
View ArticleRe: Planned Ind Reqs (PIRs) mismatch when transferred from APO DP to ECC
Hi All, Thanks for your response. I found a SAP note 2005183 to fix this issue. I'm still going through approval process to apply note. However, I'm positive this note would fix my issue. Regards...
View ArticleRe: Planned Ind Reqs (PIRs) mismatch when transferred from APO DP to ECC
Thanks for update. so one more SAP bug
View ArticleRe: Planned Ind Reqs (PIRs) mismatch when transferred from APO DP to ECC
Yes, Note 2005183 fixed this issue